Q: Will the City provide a project map or diagram showing the full alignment and connections?
A: Refer to OCTA’s 2025 Master Plan of Arterial Highways (Open in new window).
Q: What is the anticipated timeline for project completion?
A: Completion of the Project is scheduled for April 2027. Completion of Marine Way within the Great Park and connection to the Marine Way Grade Separation is anticipated summer of 2027.
Q: Will the project be delivered within a reasonable timeframe, or is it a longer-term effort?
A: Due to the nature of the Project’s construction (built on site and slid into place), the construction duration is shorter than typical grade separation projects.
Q: Why is this project being prioritized at this time compared to other infrastructure needs?
A: The Project is necessary to mitigate traffic congestion within and around the Great Park.
Q: How does this project relate to upcoming regional events and long-term planning efforts?
A: The roadway and resulting project have been previously assumed and analyzed in the City’s General Plan and the County’s Master Plan of Arterial Highways. As a result, all planning and environmental approvals, including analysis of traffic, have included the project, and all planned regional and city growth is assumed to occur.
Q: We heard there are three stages for this project. Can you outline what the stages are?
A: In general, the Project consists of constructing and installing the Borrego Channel structure, realigning the existing Borrego Channel through the new structure, constructing and installing the Marine Way Grade Separation structure, and lastly, realigning existing Marine Way through the new structure. Keep in mind that work on these components can occur at the same time, but cannot be finished until the previous is completed.
Q: Can you also share any scope modifications that have occurred recently?
A: There haven’t been any recent project scope modifications.
Q: Is there a timeline for when the train tracks will be closed during construction?
A: Yes. Metrolink provided a calendar with allowable 53-hour Absolute Work Windows (AWWs). Installation of the Borrego Channel structure is scheduled during a September 12-14, 2026 AWW. Installation of the Marine Way structure is scheduled during a November 7-9, 2026 AWW.
Q: I heard this is not a common construction practice on the West Coast. Is that correct, and if so, why?
A: Correct. Typically, grade separations are constructed by rerouting railroad tracks around the work area, constructing the new grade separation structure, and then restoring the original track alignment. The Marine Way Grade Separation structure will be constructed on site and moved into place during a 53-hour railroad shutdown, eliminating the need to construct and remove temporary tracks.